FILL 10128
Summary
start: September 19, 2024 05:54:26 AM UTC
end: September 19, 2024 02:28:42 PM UTC
duration: 0 days 08:34:15.834125
tags:
- BEAM_COMMISSIONING
comments:
- Commissioning of pp reference run (optics commissioning at injection and flattop)