FILL 10460
Summary
start: April 14, 2025 05:32:14 PM UTC
end: April 14, 2025 09:06:27 PM UTC
duration: 0 days 03:34:13.077000
tags:
-
BEAM_COMMISSIONING
-
VDM
comments:
-
test with INDIV to investigate B2 dump at start of ramp, beam lost when blowup activated regardless of bunch length target or funny BQM readings, traced back to issues with the phase loop and possible synchro error issue before.
-
still BQM reading glitches in the bunch length
-
B2 tunes FF based on previous ramp with INDIVs in both beams
Cycle duration

Beta-functions at the IPs

Crossing angles

Octupoles

Trims
Tune trims

Chromaticity Trims

Intensity
Cycle intensity

Violin BBB intensity

Bunch Length

Bunch Length Fill

Emittance
B1 along the cycle

B2 along the cycle

Summary violin plot

Bunch brightness

Beam properties summary