FILL 10733
Summary
start: June 19, 2025 02:14:48 AM UTC
end: June 19, 2025 06:07:30 AM UTC
duration: 0 days 03:52:41.712125
tags:
- MD
comments:
-
MD15603 (commissioning of ramp in steps)
-
B1 to 1 TeV and measure b3 decay to do some feedforward. Then did betatron LM and as there was still some time before the access started the ramp to 2 TeV.
-
Unfortunately, got dumped for a beta* interlock on TCT (not masked) due to inconsistent setting generation.
-
The measurements above are useful, but overall the activity did not take place.